1. Within six months of the completion of a capacity analysis in accordance with Article 24, the infrastructure manager shall establish a capacity-enhancement plan for elements of railway infrastructure declared as congested, in accordance with Article 23.
The capacity-enhancement plan shall identify:
(a) the reasons for the congestion;
(b) the likely future development of traffic;
(c) the constraints on railway infrastructure development;
(d) the options and costs for capacity enhancement, including the measures referred to in Article 24(2) and likely changes to access charges.
On the basis of a cost benefit analysis of the possible measures identified, the capacity-enhancement plan shall also determine the action to be taken to enhance railway infrastructure capacity, including a timetable for implementing the measures.
2. The capacity-enhancement plan shall be established after consultation with users of the relevant congested railway infrastructure in accordance with Article 15.
A Member State may decide that that plan shall be subject to its prior approval.
3. The Member State concerned shall take into account capacity-enhancement plans when renewing the indicative railway infrastructure development strategy referred to in Article 8(1) of Directive 2012/34/EU.
The European Coordinator concerned shall take into account the capacity-enhancement plan in its work plan referred to in Article 53 of Regulation (EU) 2024/1679.
4. Without prejudice to Article 42 of this Regulation, the infrastructure manager shall cease to levy any charges for the relevant railway infrastructure under Article 31(4) of Directive 2012/34/EU in one of the following cases:
(a) the infrastructure manager does not establish a capacity-enhancement plan;
(b) the infrastructure manager does not make progress with the measures identified in the capacity-enhancement plan.
5. Notwithstanding paragraph 4, the infrastructure manager may, subject to the approval of the regulatory body, continue to levy the charges in one of the following cases:
(a) if the capacity-enhancement plan cannot be realised for reasons beyond its control;
(b) if the options available are not economically or financially viable.